North Ocean Shipping v Hyundai Construction (The Atlantic Baron) [1979] QB 705
The defendants agreed to build a ship for the claimants for a certain price specified in US dollars. After entering the contract the US dollar was devalued by 10%. The defendants threatened not to complete unless the claimants paid an additional 10% on the contractually agreed price. The claimants had a valuable charter lined up so agreed to pay the additional sums and did pay them without protest. 8 months after delivery of the ship the claimants brought an action to recover the additional sums paid.
Held: The contract was voidable for duress, however, since the claimants had left it so long in bringing their claim they had affirmed the contract and lost their right to rescind.